Power Profile

Phase	No. of Days	Subsystem		Ave pwr		Peak Pwr

1. Journey from earth orbit to moons surface

	5 earth days
			GN&C			10		45
			Computers		30		60
			Thermal			30		45
			Communications		50		70
			Cameras			5		10
			Propulsion		-		150
		         		Total	135		380


2. Oxygen Search

	14 lunar days
			Oxygen Plant		?		50  5 runs @ 4hrs. each
			Computers		30		60
			Thermal			40		30
			Communications		50		70
			Cameras			5		10
			
					Total	125 		235

3. Lunar Night

	14 lunar days
			Computers		30		
			Thermal			30		
			Communications		23		
			Camera			5		10 for 2 days
					Total	88		10