Rover Subsystem - Texas Tech 3/1/96 Progress Report


From: Richard Eddings richeng@HUB.ofthe.NET

Most of the week was spent preparing for construction of the prototype. The initial Pro-E drawings of the frame were completed, however, I do not have the file to send. The thermal calculations are in progress, but, due to some outside distractions, I did not complete them. A test setup of the wheel is being designed to help us improve our drivetrain design. next: Next week, the Pro-E file for the frame will be modified and submitted. The thermal calculations will be inserted into an Excel document and sent as well. The Antenna array will be finalized also.

Mass: 10 kg
Power: 25 W